Set up a project structure faster

Falcon allows you to copy elements in the project tree.
-Copy individual measures into another measure package in the same project or into a package of another project.
-You can also copy an entire measure package to another project.
-At the moment you cannot copy whole projects.

Copy elements

  1. Right-click an item in the project tree. 
  2. Then click "Copy to" in the drop-down list.
  3. Finally, select a level to which you want to copy the selected item.

Note: After copying an element, Falcon automatically recalculates all traffic lights in the background. Therefore, it may take some time until all values have been calculated accordingly. Just wait a bit and then refresh Falcon.

Did this answer your question?