If you want to prevent a measure from being included in the traffic light calculations, you can simply prevent this. To do this, proceed as follows:

  1. In the tree, right-click on the desired measure. 
  2. In the right-click menu, select the option "Pause / Activate". You can tell that the task is paused by the crossed-out traffic lights in the tree.

If you want to include the measure in the aggregation again, proceed in the same way.

 Note: Pausing/activating the aggregation is inherited downwards in the tree. For example, you can pause an entire measures package with just one click.