Attention! You must always save entries in the effects table! You must always save entries in the effects table, otherwise they will be lost. Pressing the Enter key is not sufficient!

If you want to enter effects, this happens on measure level (the lowest level in the tree). All superordinate levels represent aggregations. The procedure is very simple. Just follow the steps below

  1. Select the "Effects" area of a task.
  2. In the effects table that is displayed, you can see all the effects that you have created at project level and as many columns as months the project will last.
  3. By simply clicking on a field within the table, you can enter budget values for an effect.
  4. Falcon automatically calculates the delta between planned and actual values and adds the effects to higher project levels.