If the activities in the schedule have been entered directly into the plan, they can be converted to actual/forecast with just one click. This activates the traffic lights for all affected activities in the schedule.

  1. Right-click on the element in the tree for which you want to transfer activities from the plan to actual/forecast. 
  2. Select "Transfer values" and then "Set schedule actual/forecast" from the menu.

Attention: The action is carried out for all lower levels as well. This means that if you execute the action at project level, it will actually be executed for all measure packages and measures in the project. The same applies to measure packages. Existing values won't be overwritten. 